1. One complete
set of alluvial gold processing equipment delivered to
Ethiopia in 1995, which included feeder, trommel, pulse-sluice,
jig and
belt conveyer.
2. One complete set of gold processing equipment delivered to
Ubilia gold
mine in Irkutsk region of Russia in 1997, which included feeder,
ball
mill, classifier, jig and sampler. The magnetic anti-wear
liners were
installed for the ball mill. The capacity of the processing
plant is 300
tones /per day. After the processing plant was in operation,
the
equipments were in good condition, and later the plant is
shut down due
to the geological gold grade was changed to the minus.
3. One complete set of gold Carbon In Pulp processing equipment
delivered
to Chukotka closed to North Pole region of Russia in 1999.
Until now, the
plant is in operation.
4. One bucket ladder dredge delivered to Sevzoto placer gold
mine in Bodaibo
region of Russia in 2000, the capacity of the bucket is 60
litters, and
the jigs were adopted for processing, which is better for
fine particle
size gold recovery. Currently, the dredge is in good working
condition.
5. One complete set of jig for the renovation of existing 300
litters gold
dredge delivered to Sevzoto placer gold mine in Bodaibo region
of Russia
in 2000.
6. One set of derock equipment for gravel treatment delivered
to Sevzoto
placer gold mine in Bodaibo region of Russia in 2000. So far,
the
equipment is in operation.
7. One complete set of processing equipment delivered to Badaibo
region of
Russia in 2000, which included ball mill and jigs. The capacity
of the
plant is 300 tones /per day.
8. Two complete set of gold processing equipment delivered
to Amur gold
mine in Chabarovsk region of Russia in 2000 and 2002 respectively,
which
included jaw crusher, semi-auto genous mill, ball mill, classifier,
agitator, carbon desorbs electric winning system and press
filter. The
capacities of the both processing plants are respectively
800 tones /per
day and 750 tones /per day. The both plants are in operation
now.
9. One complete set of gold processing equipment delivered
to Pofrovski in
the Amur state of Russia in 2000, which included jaw crusher,
semi-auto
genous mill, ball mill, classifier, belt conveyor, electronic
scale, sand
pump and press filter. The capacity of the plant is 3000 tones
/per day.
At present, the plant is in operation.
10. One complete set of gold mining and processing equipment
delivered to
Vysochaishy in Bodaibo region of Russia in 2002, which included
Bulldozer, wheel loader, excavator, feeder, auto genous mill,
ball mill,
classifier, shaking table, jig, double impellers high efficient
leaching
absorb tank, chemical pumps, sand pump, belt conveyor, electronic
scale,
high temperature and high efficient desorbs electric winning
system,
carbon regeneration kiln and press filter. The capacity of
the plant is
3000 tones /per day. Now the earth moving equipments is in
operation and
the processing equipments will be commissioned in May of 2003.
|
|